Seaway Heavy Lifting, part of Subsea 7 Renewables & Heavy Lifting Business Unit, is awarded the sizeable contract for the transport and installation of 90 WTG foundations and two offshore substations  Read more
Our highly skilled and motivated on- and offshore professionals are passionate to work on detailed, effective and maximum added value solutions.
We in-house operate high quality fulfilment equipment like hammers, upending tools, generators and ILT’s in order to work as efficient as possible.
Scope Topsides and living quarter’s installation
Client Newfield Peninsula Malaysia Inc.
Dimensions
Topside weight
555Mt 
Number of modules1

Waterdepth 70m (LAT)
Fabrication

Harland & Wolff Belfast (N.I)

Installation
Period 18th – 21st March, 2008
Offshore Installation
Duration/Speed 3 days (74 hours)