Seaway Heavy Lifting, part of Subsea 7 Renewables & Heavy Lifting Business Unit, is awarded the sizeable contract for the transport and installation of 90 WTG foundations and two offshore substations  Read more
Our highly skilled and motivated on- and offshore professionals are passionate to work on detailed, effective and maximum added value solutions.
We in-house operate high quality fulfilment equipment like hammers, upending tools, generators and ILT’s in order to work as efficient as possible.
Scope Transport and installation of Substation platform
Client Hollandia
Dimensions
Jacket weight 563Mt 

Pile dimensions

4 main piles  LS + add on

LS 108 ao 55 
Pile length
90m
Pile diameter
1524mm 


Waterdepth --- m (LAT)
Installation Period

16th – 26th September, 2012