Seaway Heavy Lifting, part of Subsea 7 Renewables & Heavy Lifting Business Unit, is awarded the sizeable contract for the transport and installation of 90 WTG foundations and two offshore substations  Read more
Our highly skilled and motivated on- and offshore professionals are passionate to work on detailed, effective and maximum added value solutions.
We in-house operate high quality fulfilment equipment like hammers, upending tools, generators and ILT’s in order to work as efficient as possible.
Scope MSF,modules and flare installation
Client TL Offshore
Dimensions
Topside weight
2320Mt 
Module No. 1
1740Mt
Module No. 2
530Mt
Module No. 3
710Mt
Module No. 4
1475Mt
 Module No. 51750Mt
Flareboom
125Mt
Number of modules
5


Waterdepth 43m (LAT)
Installation Period

3rd February – 14th March 2008

 Duration / Speed  40 days (969 hours)